Milestone Contractors will begin work on the 2018 City Overlay Program – Phase 1.

Friday July 13, 2018
Patching
1st Street from Franklin Street to Lafayette Street
5th Street from Lafayette Street to Pearl Street
7th Street from Franklin Street to Lafayette Street

Monday July 16, 2018 –  Wednesday July 18, 2018
Patching
Forrest Drive from Maple Street to 27th Street
Illinois Street from Brooks Street to Gladstone Avenue

Beginning Monday July 16, 2018
Crews will begin replacing concrete cross gutters on Flintwood Drive at the intersections of Yellowwood Drive, Magnolia Street, 29th Street and Miami Drive.
Construction on one intersection at a time and that intersection closed.
Approximately, one week later crews will begin installing underdrains at these same locations.

*Please reduce speeds and use extra caution while in the work zones.
*Please follow construction signage and obey flag personnel.