RE-01: Continue to encourage, support, and incentivize infill development

Category: Real Estate
Implementation Phase: Near-term (0-2 years) Status: In Progress
Partners: Community Development, Planning Department, Office of Downtown Development


May 1, 2026 | City of Columbus reports:
PACT Program in place. Planning Department’s new construction permitting process flow chart released.

RE-02: Incentivize housing development (townhomes to multifamily)

Category: Real Estate
Implementation Phase: Near-term (0-2 years) Status: In Progress
Partners: City of Columbus, Columbus Redevelopment Commission


May 1, 2026 | Columbus Redevelopment Commission reports:
Ten20 North under construction at 11th and Washington St.

RE-03: Target diversity of shops, eateries, and entertainment venues

Category: Real Estate
Implementation Phase: Near-term (0-2 years) Status: In Progress
Partners: Office of Downtown Development


April 1, 2026 | Office of Downtown Development reports:
St. Denis & other businesses in discussion to open downtown.

June 1, 2026 | Private or nonprofit operator reports:
At Home with Heartland Backroads Boutique opened at 401 Washington St.

RE-04: Support improvements of privately-owned buildings

Category: Real Estate
Implementation Phase: Near-term (0-2 years) Status: In Progress
Partners: Office of Downtown Development


May 1, 2026 | Office of Downtown Development reports:
ODD Grant Program funds renewed in Q4 2025. Robust list of applicants.

RE-05: Develop process for City to exit role as landlord/divest property

Category: Real Estate
Implementation Phase: Near-term (0-2 years) Status: Not Started
Partners: City of Columbus, Columbus Redevelopment Commission


June 1, 2026 | City of Columbus reports:
The City of Columbus is considering this recommendation

RE-06: Prioritize Strategic Plan projects for TIF funding

Category: Real Estate
Implementation Phase: Near-term (0-2 years) Status: Not Started
Partners: Columbus Redevelopment Commission


June 1, 2026 | City of Columbus reports:
With the recent release of an RFQ and RFI for interest from potential lead developers, the City will be able to prioritize large scale projects

RE-07: Encourage workforce and affordable housing downtown

Category: Real Estate
Implementation Phase: Near-term (0-2 years) Status: Not Started
Partners: Community Development, Columbus Redevelopment Commission


RE-08: Relocate USPS facilities and redevelop post office site

Category: Real Estate
Implementation Phase: Near-term (0-2 years) Status: Not Started
Partners: City of Columbus, Columbus Capital Foundation


RE-09: Activate former Sears parking lot with temporary ‘eatertainment’

Category: Real Estate
Implementation Phase: Near-term (0-2 years) Status: Completed
Partners: Columbus Redevelopment Commission, Office of Downtown Development


April 1, 2026 | Columbus Redevelopment Commission reports:
Food Truck Festival 3rd Thursday April-October

RE-10: Redevelop former Sears site with expanded commercial uses

Category: Real Estate
Implementation Phase: Near-term (0-2 years) Status: Planning
Partners: Columbus Redevelopment Commission, private developers


RE-11: Redevelop Irwin Block site with housing

Category: Real Estate
Implementation Phase: Near-term (0-2 years) Status: Planning
Partners: Columbus Capital Foundation, private developers


December 1, 2025 | Columbus Capital Foundation reports:
IU Architecture Studio studied the Irwin Block and presented recommendations in December 2025.

RE-12: Develop housing on the 2nd and Franklin parking lot

Category: Real Estate
Implementation Phase: Near-term (0-2 years) Status: Planning
Partners: Columbus Redevelopment Commission, private developers


RE-13: Pursue business for built retail west of The Taylor (Urban Grocer)

Category: Real Estate
Implementation Phase: Near-term (0-2 years) Status: Not Started
Partners: Flaherty & Collins


June 1, 2026 | Other community partners and organizations reports:
Breeden Commercial Realtors is pursuing a tenant for this space.

RE-14: Attract more breweries, cideries, and distilleries

Category: Real Estate
Implementation Phase: Near-term (0-2 years) Status: In Progress
Partners: Community Development, Private Developers, Office of Downtown Development, Chamber of Commerce


April 1, 2026 | Private developers reports:
St. Denis wine bar with wine tastings opened in April 2026.

RE-15: Formal partnership between ODD and Community Development

Category: Real Estate
Implementation Phase: Near-term (0-2 years) Status: Completed
Partners: Community Development, Office of Downtown Development


January 1, 2026 | Department of Community Development reports:
Winter Market, 2nd Floor Review, Developer Visits, Alley 54, Grant Program, CD203 Implementation Efforts

RE-16: Support presence and expansion of Yes Cinema

Category: Real Estate
Implementation Phase: Short-term (3-5 years) Status: Planning
Partners: Columbus Redevelopment Commission


RE-17: Develop 2nd Street site (east of The Taylor) for multifamily housing

Category: Real Estate
Implementation Phase: Short-term (3-5 years) Status: Not Started
Partners: Columbus Redevelopment Commission, private developers


RE-18: Continue efforts to attract urban grocer to Opportunity Sites

Category: Real Estate
Implementation Phase: Short-term (3-5 years) Status: Not Started
Partners: Office of Downtown Development, Chamber of Commerce


RE-19: Encourage introduction of co-working space

Category: Real Estate
Implementation Phase: Short-term (3-5 years) Status: In Progress
Partners: Office of Downtown Development


April 1, 2026 | Private developers reports:
Beck Rocker developing 3rd floor small office and co-working space.

RE-20: Grow identity as center of creative arts and design

Category: Real Estate
Implementation Phase: Short-term (3-5 years) Status: Not Started
Partners: Office of Downtown Development


June 1, 2026 | Columbus Area Arts Council reports:
The CD2030 implementation team is evaluating Columbus’s Arts and Culture District designation and exploring opportunities to strengthen its identity and impact.

RE-21: Encourage redevelopment of Downtown Southeast for urban housing

Category: Real Estate
Implementation Phase: Short-term (3-5 years) Status: Not Started
Partners: City of Columbus, private developers


RE-22: Develop multi-purpose market hall at western end of 4th Street

Category: Real Estate
Implementation Phase: Short-term (3-5 years) Status: Planning
Partners: City of Columbus, Columbus Redevelopment Commission


December 1, 2025 | Department of Community Development reports:
Winter Market Pilot collaboration was very successful, consistently. Remaining action steps are complete.

RE-23: Relocate Visitors Center to Washington Street location

Category: Real Estate
Implementation Phase: Short-term (3-5 years) Status: Not Started
Partners: Columbus Area Visitors Center


RE-24: Develop hotel and conference center on former Sears parking lot

Category: Real Estate
Implementation Phase: Medium-term (6-9 years) Status: Planning
Partners: Columbus Redevelopment Commission, private developers


RE-25: Develop edges of Cummins Brown St lot/consolidate parking

Category: Real Estate
Implementation Phase: Longer-term (10+ years) Status: Not Started
Partners: Cummins


RE-26: Develop residential neighborhood on former wastewater site

Category: Real Estate
Implementation Phase: Longer-term (10+ years) Status: Planning
Partners: Columbus Redevelopment Commission, private developers


RE-27: Encourage specialty food/beverage along riverfront

Category: Real Estate
Implementation Phase: Longer-term (10+ years) Status: Not Started
Partners: City, Redevelopment Comm., private developers


RE-28: Densify sites straddling 2nd Street (Brown to Lindsey)

Category: Real Estate
Implementation Phase: Longer-term (10+ years) Status: Not Started
Partners: City, private landowners, businesses


RE-29: Redevelop Franklin Street lot into parking structure

Category: Real Estate
Implementation Phase: Longer-term (10+ years) Status: Not Started
Partners: City of Columbus, Columbus Redevelopment Commission


PR-01: Advance wayfinding planning and interpretive signage

Category: Public Realm
Implementation Phase: Near-term (0-2 years) Status: In Progress
Partners: Visitors Center, City of Columbus


May 1, 2026 | Columbus Area Visitors Center reports:
Design work underway for Downtown Wayfinding

PR-02: Extend People Trail along 1st Street

Category: Public Realm
Implementation Phase: Near-term (0-2 years) Status: Not Started
Partners: Parks and Recreation, Planning


June 1, 2026 | City of Columbus Department of Public Works reports:
As part of ongoing gateway improvements, the team is reviewing options for signage and pavement markings to better connect and highlight the 1st Street section of the People Trail.

PR-03: Conduct Mill Race Park Master Plan

Category: Public Realm
Implementation Phase: Near-term (0-2 years) Status: In Progress
Partners: Parks and Recreation


April 1, 2026 | Department of Parks and Recreation reports:
Mill Race Park, along with Donner Park and the Parks Strategic Plan master planning efforts starting in April 2026.

PR-04: Improve Mill Race arrival at 5th and architectural gateway

Category: Public Realm
Implementation Phase: Near-term (0-2 years) Status: In Progress
Partners: Parks and Recreation, Community Devleopment


May 1, 2026 | Columbus Park Foundation reports:
A City grant for clean up at the 5th Street entrance to Mill Race Park

PR-05: Maintain Water Street site as forested buffer

Category: Public Realm
Implementation Phase: Near-term (0-2 years) Status: Not Started
Partners: Redevelopment Commission, private developers


June 1, 2026 | City of Columbus Department of Public Works reports:
This forested buffer is being maintained by the Department of Public Works

PR-06: Convert streets from one-way to two-way (Brown, Lindsey, Franklin)

Category: Public Realm
Implementation Phase: Short-term (3-5 years) Status: Not Started
Partners: City of Columbus, Public Works


PR-07: Improve arrivals at key gateways (11th, Stewart Bridge, etc.)

Category: Public Realm
Implementation Phase: Short-term (3-5 years) Status: In Progress
Partners: City of Columbus, Public Works, Engineering, Arts Council


September 1, 2025 | Columbus Area Arts Council reports:
3rd St. Dancing C’s Mural complete

May 1, 2026 | Columbus Redevelopment Commission reports:
2nd St. Thoroughfare traffic calming and other improvements underway

June 1, 2026 | Columbus Redevelopment Commission reports:
The east Gateway into Downtown Columbus from State Road 46 is being renovated through the Riverfront project, the 2nd St. Thoroughfare project, and the anticipated Gateway Entrance Plaza renovation. More information can be found at the Redevelopment Commission’s website.

PR-08: Streetscape improvements: 4th Street

Category: Public Realm
Implementation Phase: Short-term (3-5 years) Status: Not Started
Partners: City of Columbus, Public Works


PR-09: Streetscape improvements: 5th Street (Avenue of Architects)

Category: Public Realm
Implementation Phase: Short-term (3-5 years) Status: Not Started
Partners: City of Columbus, Public Works


June 1, 2026 | Columbus Area Visitors Center reports:
Visit Columbus has enhanced the Irwin Block building with window graphics showcasing the iconic spaces and places that make up the Avenue of the Architects.

PR-10: Build destination children’s play area and splash pad in Mill Race

Category: Public Realm
Implementation Phase: Short-term (3-5 years) Status: Planning
Partners: Parks and Recreation


PR-11: Establish more trail connections to/through downtown heart

Category: Public Realm
Implementation Phase: Short-term (3-5 years) Status: Not Started
Partners: Parks and Recreation, Parks Foundation


PR-12: Create stronger dialogue between Mill Race and Flatrock River

Category: Public Realm
Implementation Phase: Short-term (3-5 years) Status: Not Started
Partners: Parks and Recreation


PR-13: Build high-design bus shelters at downtown stops

Category: Public Realm
Implementation Phase: Short-term (3-5 years) Status: Not Started
Partners: City Public Works, ColumBUS Transit


June 1, 2026 | ColumBUS Transit reports:
With the implementation of the new ColumBUS Loop System, the Transit Department is evaluating opportunities for additional downtown bus shelters and will again partner with the J. Irwin Miller Architecture Program at IU Columbus on the design effort.

PR-14: Replace downtown street trees with native species

Category: Public Realm
Implementation Phase: Short-term (3-5 years) Status: Not Started
Partners: City of Columbus, Public Works


PR-15: Explore designation of a rail quiet zone

Category: Public Realm
Implementation Phase: Short-term (3-5 years) Status: Planning
Partners: City of Columbus


PR-16: Streetscape improvements: Washington Street

Category: Public Realm
Implementation Phase: Medium-term (6-9 years) Status: Not Started
Partners: City of Columbus, Public Works


PR-17: Streetscape improvements: 2nd and 3rd Streets

Category: Public Realm
Implementation Phase: Medium-term (6-9 years) Status: Not Started
Partners: City of Columbus, Public Works


PR-18: Create pedestrian bridge connection from 4th St to Mill Race Park

Category: Public Realm
Implementation Phase: Medium-term (6-9 years) Status: Not Started
Partners: Columbus Redevelopment, Cummins, private developers


AP-01: Expand/promote City community calendar

Category: Activation
Implementation Phase: Near-term (0-2 years) Status: Completed
Partners: Columbus Visitors Center


March 18, 2026 | Columbus Area Visitors Center reports:
The Visit Columbus website can be used to find events and to add an event

AP-02: Activate Courthouse Lawn, City Hall Green, Entrance Plaza

Category: Activation
Implementation Phase: Near-term (0-2 years) Status: Planning
Partners: Arts Council, Visitors Center, Office of Downtown Development


May 1, 2026 | Office of Downtown Development reports:
ODD is activating the north side of the Irwin Block with a small City grant to the Visitors Center to temporarily activate the space.

May 1, 2026 | City of Columbus reports:
A new ramp at the front of City Hall is being built. This will allow for better activation of the City Hall steps and lawn .

AP-03: Expedited approval/lower criteria for outdoor events

Category: Activation
Implementation Phase: Near-term (0-2 years) Status: Completed
Partners: City of Columbus


May 1, 2026 | City of Columbus Department of Engineering reports:
Community feedback complete, the policy is updated and communications are underway.

AP-04: Program/promote DORA district opportunities

Category: Activation
Implementation Phase: Near-term (0-2 years) Status: In Progress
Partners: City of Columbus, Arts Council, Visitors Center, Office of Downtown Devleopment


May 1, 2026 | City of Columbus reports:
Working with City, ODD and CAAC to implement branding. ODD will promote DORA at their outdoor events.

AP-05: Activate Mill Race Park with new/refreshed programming

Category: Activation
Implementation Phase: Near-term (0-2 years) Status: In Progress
Partners: Parks and Recreation, Arts Council


May 1, 2026 | Department of Parks and Recreation reports:
New playground equipment installed. Community ribbon cutting is on 5/12.

AP-06: Establish Mill Race Park as focus of community organizations

Category: Activation
Implementation Phase: Near-term (0-2 years) Status: In Progress
Partners: Parks and Recreation, Parks Foundation


July 1, 2026 | Department of Parks and Recreation reports:
River Rats organizing, planned community-wide launch July 1, 2026.

AP-07: Support rehabilitation of Crump Theater

Category: Activation
Implementation Phase: Near-term (0-2 years) Status: Planning
Partners: Crump Center for Performing Arts


May 1, 2026 | Crump Center for the Performing Arts reports:
Design completion and fundraising efforts continue. Final spring programming wrapping up in May 2026.

AP-08: Enhance 5th Street identity with architecture/design programming

Category: Activation
Implementation Phase: Near-term (0-2 years) Status: In Progress
Partners: Visitors Center, Community Development


May 1, 2026 | Columbus Area Visitors Center reports:
Visit Columbus is installng vinyl on the Irwin Block building highlighting the Avenue of the Architects

AP-09: Brand/program open space at Irwin Bank (5th and Jackson)

Category: Activation
Implementation Phase: Near-term (0-2 years) Status: Not Started
Partners: Cummins


AP-10: Bolster commitment to local business (Shop Downtown campaign)

Category: Activation
Implementation Phase: Near-term (0-2 years) Status: In Progress
Partners: Chamber of Commerce, Office of Downtown Development


May 1, 2026 | Chamber of Commerce reports:
Holiday 2025 collaboration to support shop local campaign, Catalyst 100 to support local business (including 25% downtown)

May 1, 2026 | Downtown business owners reports:
First Thursday Events occuring each month

AP-11: Activate alley between Jackson Garage and Washington Street

Category: Activation
Implementation Phase: Near-term (0-2 years) Status: Planning
Partners: Private landowners, Office of Downtown Development, City of Columbus


May 1, 2026 | Private developers reports:
Early designs shared and in-process

AP-12: Enhance connectivity between downtown and Nexus Park

Category: Activation
Implementation Phase: Short-term (3-5 years) Status: In Progress
Partners: Visitors Center, City of Columbus


AP-13: Hire a coordinator for downtown programming/events

Category: Activation
Implementation Phase: Short-term (3-5 years) Status: Planning
Partners: City of Columbus, Arts Council, Heritage Fund


May 1, 2026 | Columbus Area Arts Council reports:
Arts & Culture group and City discussing position and where it best fits.