Our River…
Our Riverfront
Current Project Timeline
Phase IV – Construction Phase Services
September 2024 | Bid Prequalification Process and Advertising
October 2024 | Bids Open
December 2024 | CMc Contract Issued
January 2025 | Construction Prep
March 2025 | Mobilization / Construction Begins
Phase III – Final Design and Engineering
January – October 2020 | Construction Documents
Period of Regulatory Correspondence
December 2022 | Receive Permits from INDNR
August 2023 |Received Permits from IDEM
September 2023| Received Permits from USACE
November 2023 | Engage CMc
October 2019
Project Drawings Submitted for Permitting
On October 24, 2019, the design team official submitted the project to the INDNR for permits.
January 2018 – September 2019
Riverfront Master Plan Presented
On January 22, 2018, Hitchcock Design Group presented the Columbus Redevelopment Commission with the final concept for the Columbus Riverfront project. Go back to the top of the page for the final concept presentation.
Riverfront Plan Refined & Developed
After receiving feed back from the Master Plan presentation, the design team began design development of the Riverfront. This months long phase required coordination with State Agencies and Community Groups. Development of the project led to four Agency Requested Modifications to the Master Plan:
Modification #1
– Incorporated fish passage channel
– Moved pedestrian trail above the ordinary high water mark
– Eliminated mid-river universal access point
Modification #2
– Moved pedestrian trail towards the top of the bank
– Provided riparian habitat corridor along river bank
Modification #3
– Incorporated rock arch ramp structure
– Reduced amount of grout required in the structure
Modification #4
– Reduced amount of grout required in the structure
November 2017
Public Open House
On November 8th, Hitchcock Design Group presented their concept for the re-envisioned Riverfront! More than 75 people attended the open house to hear an informative presentation and ask questions.
Riverfront Design Team meets with the Columbus Redevelopment Commission (CRC)
On November 30th, 2017, Hitchcock Design Group presented their concept for the re-envisioned Riverfront to the Columbus Redevelopment Commission!
Presentation Boards
Graphic Renderings
October 2017
Riverfront team meets with regulatory agencies
The Columbus Riverfront team met with several regulatory agencies about the Riverfront project. Folks from IDEM, DNR, and USACOE gathered on site to review the preliminary concepts, walk the site, and give their first impressions of the project and how it looks through ‘regulatory lenses’. We had some great discussions, learned some new information, and are ready to move forward with completing the conceptual vision of the Riverfront! Listed below are the agencies that were present at the meeting:
US ACOE
DNR – Division of Water
DNR – Fish & Wildlife
DNR – Division of Historic Preservation and Archeology
IDEM – Land Quality
IDEM – Water Quality
July 2017
A Preliminary Concept is Chosen!
The design process for a project of this magnitude involves an abundance of research, collaboration, and input from stakeholders like you. After months of research, Hitchcock Design Group has evaluated the collected data to develop a conceptual design for the east and west banks of the river.
The sinuosity of this design concept mimics the smooth and flowing lines that define Mill Race Park, and uses a similar and readily available material pallet of limestone and concrete. By aesthetically tying the Columbus Riverfront to Mill Race Park, Hitchcock Design Group is creating a cohesive aesthetic along the Riverfront, providing a seamless transition while traveling in and along the river.
April 2017
Community Workshop
We had a great turn out for our community workshop on April 5th and 6th! Click on the link below to view the presentation that was given at the workshop.
Redevelopment
Location:
123 Washington Street
Columbus, Indiana 47201
(812) 376-2547
Fax: (812) 375-2565
TDD: Call 711
Contact Us
Hours
Monday – Friday
8:00 a.m. – 5:00 p.m.